Infographic 1 – Deployment timelines@1x (1)

Infographic comparing modular and traditional data center deployment times, from 24–36 months down to weeks

How long a data center takes to deploy. A traditional build takes 24–36 months, like-for-like modular 9–18 months, and a prefabricated modular facility 4–6 months. Standard modules leave the factory in 10–16 weeks, and containerized or micro data centers run within weeks once the site is ready.